PV MANUFACTURING EQUIPMENT
My account中国工厂入驻 Create RFQ

EQUIPMENT SERIES

HORAD ICB lead-straightening station

Suzhou HORAD New Energy Equipment Co., Ltd. ↗

HORAD's lead-straightening station undoes the protection put on at the bending step. Three mechanisms pull off tape or high-temperature cloth together, the leads are aligned, and shaping starts. An optional heater with live temperature display helps where site conditions call for it.

You buy either the tape-peeling or the cloth-peeling version. HORAD publishes no peel force, finished lead tolerance, cycle time or proven heating recipe, and the tape or cloth must match the size the chosen version expects.

General illustration of module assembly equipment, not a photograph of this model. Ask the manufacturer for current photographs and layout drawings of the configuration offered.

START WITH YOUR PRODUCTION TASK

Tell HORAD how the leads and their protection arrive, pick tape or cloth tooling, and test peeling and final lead shape, keeping any heat inside your approved module process.

SOURCE-LINKED DATA

Published specifications

Values below are published by the manufacturer, each with the date its source was checked. Ask for the figures that apply to your configuration and material in the quotation.

The manufacturer has not published a complete specification table for this entry. Request the exact offered drawing and operating limits.

See sources and check dates ↓

01 · Manufacturer information

Peel, align, then shape the leads

The station comes in a tape-peeling or a cloth-peeling version; you choose one. Three mechanisms strip the protection off at once, the leads are aligned, and the shaping tools go to work. Servo correction, board-type changeover and simultaneous loading and unloading are listed too. Once shaped, the leads go on to HORAD's junction-box mounting station, where the box has to drop over them without forcing.

A heating module runs from 0 to 400°C with a live display. HORAD says whether to switch it on depends on conditions at your site. Treat 400°C as the top of the dial. Ask HORAD what temperature the lead itself reaches, for how long, how even the heat is, and what your cells, films and solder joints can take.

Source: HORAD ICB lead-straightening product page

02 · Manufacturer information

Lead straightener specification

Lead straightener specification
ItemHORAD figurePin down before ordering
High-temperature cloth40 mm long, 20 mm wide (±2 mm)Whether ±2 mm covers both sizes, and the cloth grade.
Tape20 mm wide, one side folded back ≥10 mmThe pull tab and how tape is laid at the bending step.
Heater range0–400°C, used as site conditions requireYour setpoint, the real lead temperature and dwell.
Panel size1650–2650 × 990 × 1450 mmDrawings of each module and its lead positions.
Supply / power / air380 V / 6 kW / 0.6–0.8 MPaLoad, air flow and air quality.
Machine size, L × H × W3450 × 1900 × 1850 mmSpace for operators, tools and service.
Weight2.5 TFoundation and shipping.

Source: HORAD ICB lead-straightening product page

03 · PVYard procurement analysis

What goes in and what must come out

  • Arriving protection and leads

    Name the tape or cloth, the tab size and its heat history, plus lead material, section and starting shape. Confirm which peeling version you are buying.

  • Finished lead shape

    Give the final position, angle, radius and allowed springback, and how the leads meet the junction box. Ask which tools are included and how the shape is measured.

  • Heat limits

    Decide with your process team whether heat is needed at all. If it is, ask for the sensor, its calibration and recorded recipe limits.

Source: HORAD ICB lead-straightening product page

04 · PVYard procurement analysis

Trial steps for peeling and shaping

  1. Check what arrives

    Compare the real tape fold or cloth size and the way leads are presented with the version ordered and the drawings.

  2. Watch peeling and alignment

    Look for leftover tape or cloth, bent leads and harm to the module nearby. Feed a missing tab, a half-peeled piece and an odd input.

  3. Measure the leads

    Measure position and shape against your limits and check the joints and module. Servo correction alone gives you no output tolerance.

  4. Try heat and recovery

    If heating is on, log the setpoint and the real temperatures. Trigger alarms and stops, check the restart, and keep safe manual-recovery instructions on file.

Source: HORAD ICB lead-straightening product page

05 · PVYard procurement analysis

Lead-straightening questions

Should I run the heater at 400°C?

That is the top setting. Use the temperature your own module process allows, if any.

Can one machine peel both tape and cloth?

HORAD offers one version or the other. Put your choice in the order.

Is there a finished lead tolerance?

HORAD publishes none. Write your own limit into the order and measure against it.

Source: HORAD ICB lead-straightening product page

TURN THIS INTO A CLEAR REQUEST

Ask about this product

Include the product-specific questions above and replace every bracket with your actual requirement. Save your edited text to your sourcing brief, then review it before submitting an enquiry. Saving a brief does not send it to a manufacturer.

Sources

Manufacturer information and our buying guidance are labelled section by section above. Each source below shows the date it was checked.

HORAD ICB lead-straightening product page ↗

Source check: 2026-10-11 · Peeling options, heater range, tape and cloth sizes, and the panel, utility and weight table for the straightener.

Report a correction · How we prepare listings

Compare equipment for a related task

These entries are in the same category; check each one's specifications and configuration.

Analytics preferences

Allow optional audience measurement? Your choice can be changed in the footer. Essential account cookies remain necessary for sign-in and forms.