HORAD module test-tooling circulation system

Suzhou HORAD New Energy Equipment Co., Ltd. ↗

This HORAD system keeps crossbar test tooling moving in a loop: a placing machine fits it to the panel, the module passes an inspection station, a removal machine takes the tooling off and a return line carries it back.

HORAD publishes the workflow, panel sizes, utilities and machine size. Test voltage or current, measuring range, how many jigs circulate, contact life and cycle time are left for the order.

General illustration of module assembly equipment, not a photograph of this model. Ask the manufacturer for current photographs and layout drawings of the configuration offered.

START WITH YOUR PRODUCTION TASK

Choose it if you want crossbar tooling handled automatically around your existing tester. Before ordering, send HORAD the tooling drawing and tester signals, agree how many tools circulate and how blocked returns are cleared, and ask for both in writing. Like HORAD's other back-end stations, it is built to slot into a complete module line.

SOURCE-LINKED DATA

Published specifications

Values below are published by the manufacturer, each with the date its source was checked. Ask for the figures that apply to your configuration and material in the quotation.

The manufacturer has not published a complete specification table for this entry. Request the exact offered drawing and operating limits.

See sources and check dates ↓

01 · Manufacturer information

How the crossbar tooling travels

Four pieces make up the loop. A placing machine sets crossbar tooling on the panel, a workstation downstream inspects the module, a removal machine lifts the tooling away and a return line brings it back to the start. Cameras guide the manipulator as it locates, installs and later dismantles the tooling.

HORAD sells a station with almost the same name, the singular Testing Jig Return System, which runs withstand-voltage, insulation and ground-resistance tests on a different machine table. Treat the two as separate purchases. This plural-named loop handles tooling and carries no measurement range or contact rating. Its page also mentions a cutting speed without saying what is cut, so ask HORAD what that line refers to.

Source: HORAD testing jigs return system page

02 · Manufacturer information

Listed figures for the tooling loop

Listed figures for the tooling loop
ItemHORAD listsWhat to settle for your line
WorkflowPlace tooling → downstream inspection → remove → returnWhich stations and how much return conveyor are in the supply.
CompatibilityMost test tools and long/short wiresA list of the jigs, connectors and lead lengths HORAD accepts.
Panel sizes2550–1650 × 1450–990 mmRange is written largest first; match it to your tooling and formats.
Supply / power / air380 V / 20 kW / 0.6–0.8 MPaConnected load, compressed-air consumption and dryness.
Machine size, L × H × W / weight4900 × 2000 × 2850 mm / 2.2 TWhether the footprint includes the return conveyor.

Source: HORAD testing jigs return system page

03 · PVYard procurement analysis

What HORAD needs from you

  • Crossbar drawing

    Send crossbar geometry, mass, connectors, lead lengths and the areas of the module the tooling may touch. Ask which fitting and removal grippers HORAD will supply for it.

  • Signals to the tester

    List the ready, busy and result signals your electrical tester gives, plus how contact is checked and when the tooling may be released safely.

  • Number of tools in the loop

    HORAD gives no jig count or return capacity. Agree how many tools circulate, where they buffer and where dirty or faulty tooling is pulled out.

  • Upkeep of reused tools

    Set a routine for inspecting, cleaning and replacing contacts, and a way to trace which tool tested which module.

Source: HORAD testing jigs return system page

04 · PVYard procurement analysis

Running the loop before sign-off

  1. Fix the drawings

    Lock the tooling and module drawings, the tester signal list and the layout of placing, removal and return.

  2. Fit and lift off real tooling

    Watch alignment and contact on actual modules, look for scratches on panel or tool, and confirm the tooling only comes off once the tester is in its safe state.

  3. Fill and starve the return line

    Run it full, run it empty, pull a tool out, feed a damaged one and block the downstream station. Write down how each case is cleared and the throughput reached.

  4. Swap a tool

    Reject and replace a tool in front of you, then record the settings and the first-module check to repeat after any change.

Source: HORAD testing jigs return system page

05 · PVYard procurement analysis

Questions about the tooling loop

Does it include a high-voltage tester?

No tester is described. The loop places, removes and returns crossbar tooling around whichever inspection station you run.

Is it the same machine as the singular Testing Jig Return System?

No. That station performs electrical tests and lists other utilities. Quote them as two separate items.

Will my test tools fit?

HORAD says most test tools fit but names no models. Send your crossbar and contact design and ask HORAD to confirm the fit in writing.

Source: HORAD testing jigs return system page

TURN THIS INTO A CLEAR REQUEST

Ask about this product

Include the product-specific questions above and replace every bracket with your actual requirement. Save your edited text to your sourcing brief, then review it before submitting an enquiry. Saving a brief does not send it to a manufacturer.

Sources

Manufacturer information and our buying guidance are labelled section by section above. Each source below shows the date it was checked.

HORAD testing jigs return system page ↗

Source check: 2026-10-11 · Workflow of the tooling loop, compatibility wording, panel range, utilities and machine size.

Report a correction · How we prepare listings

Compare equipment for a related task

These entries are in the same category; check each one's specifications and configuration.