HORAD module edge-tape removal station

Suzhou HORAD New Energy Equipment Co., Ltd. ↗

HORAD's tape-removal station peels edge tape off finished modules using four servo heads at once. A camera at discharge takes pictures to check the tape is gone, and the peeled tape falls into a collection box. HORAD says normal running needs no operator.

HORAD publishes no list of tapes, no peel force, no limit on leftover adhesive, no cycle time and no camera hit rate. Seeing that tape is gone and checking for adhesive film or glass chips are two separate inspections. The tape itself goes on earlier at HORAD's auto edge taping station, so trial both machines on the same roll.

General illustration of module assembly equipment, not a photograph of this model. Ask the manufacturer for current photographs and layout drawings of the configuration offered.

START WITH YOUR PRODUCTION TASK

Trial the station with your own tape after it has gone through your laminator. Set one rule for tape removed and another for a clean surface, and include jams and restarts in the trial.

SOURCE-LINKED DATA

Published specifications

Values below are published by the manufacturer, each with the date its source was checked. Ask for the figures that apply to your configuration and material in the quotation.

The manufacturer has not published a complete specification table for this entry. Request the exact offered drawing and operating limits.

See sources and check dates ↓

01 · Manufacturer information

Peel with four heads, then photograph

Four servo-controlled heads grip and pull the edge tape while servo correction keeps the panel square. Changing to another module model is built in. On the way out a camera photographs the edges to check whether the tape was torn off. A waste-tape box and a lifting platform are part of the machine.

HORAD says the station runs without operators in normal use. Somebody still empties the waste box and clears faults, so ask what those jobs involve. The camera looks for tape; clear adhesive residue, fine scratches and a half-peeled corner may need their own check. Settle what the camera judges, and when it rejects a module, with real samples in hand.

Source: HORAD edge-tape removal product page

02 · Manufacturer information

Tape remover specification

Tape remover specification
ItemHORAD figureWhat to ask
Panel size1650–2600 × 990 × 1450 mmThe length and width pairs it handles, and edge build-up.
Supply / power380 V / 8 kWInstalled and running load, and connection points.
Air pressure0.6–0.8 MPaAir flow and quality, which HORAD omits.
Machine size, L × H × W2640 × 1700 × 3840 mmAxis order as HORAD writes it; add room to reach the waste box.
Weight2.2 TFoundation and shipping details.

Source: HORAD edge-tape removal product page

03 · PVYard procurement analysis

Separate pass rules for a stripped module

  • Is the tape off?

    Say how much tape may stay, including hidden bits and corners. Prepare modules that are fully stripped, partly stripped and not stripped, and see if the camera tells them apart.

  • Is the surface clean?

    Set limits for adhesive residue, edge chips, film damage and module damage. Decide whether a second inspection should catch what the outfeed camera misses. Clean edges matter next at framing, where leftover tape can get in the way of the frame and its sealant.

  • Is the waste handled?

    Ask how much the box holds, how it is reached and what the machine does when it jams or fills. Automatic peeling still leaves an operator to carry the waste away.

Source: HORAD edge-tape removal product page

04 · PVYard procurement analysis

Trial with tape that has been through lamination

  1. Describe the incoming tape

    Record the tape grade, the edge shape, and the heat and time it saw upstream. Bring the strongest and weakest adhesion you expect.

  2. Watch each head peel

    Check all four heads, the corners and the hand-over points for tape left behind, adhesive and damage. Note the settings and every failed peel.

  3. Test the camera

    Feed known bad modules and agree what it must catch and reject. Score the camera apart from the peeling itself.

  4. Force a stop

    Try a partial peel, a jam, a full waste box and a restart. Agree how an operator steps in safely and what the first module after restart must pass.

Source: HORAD edge-tape removal product page

05 · PVYard procurement analysis

Tape-removal questions

Will the camera catch adhesive left on the glass?

HORAD shows no residue detection result. Agree a residue limit and a way to check it.

Does the station run with no attention at all?

The waste box needs emptying and HORAD does not describe that job. Ask what operators do and how faults are cleared.

If my panel fits, will my tape peel?

Panel size says nothing about adhesion. Run your own tape with its real process history.

Source: HORAD edge-tape removal product page

TURN THIS INTO A CLEAR REQUEST

Ask about this product

Include the product-specific questions above and replace every bracket with your actual requirement. Save your edited text to your sourcing brief, then review it before submitting an enquiry. Saving a brief does not send it to a manufacturer.

Sources

Manufacturer information and our buying guidance are labelled section by section above. Each source below shows the date it was checked.

HORAD edge-tape removal product page ↗

Source check: 2026-10-11 · Four-head layout, outfeed camera, waste box and the panel, utility and weight table for the tape remover.

Report a correction · How we prepare listings

Compare equipment for a related task