The gantry takes strings that a stringer has already built and arranges them on the glass. Linear motors and servo drives move it, and a camera finds position. HORAD lists horizontal and vertical layup plus AB and BC string patterns, with flipping and solder-strip cutting as add-ons.

HORAD shows this as an equipment family under a high-speed title. The page gives module format, utilities, two machine envelopes and weight. It names no cycle time, placement tolerance or breakage rate, so get those figures with the offer. For lines without BC modules, HORAD's original auto string layup gantry places strings from two sides at once.

General illustration of module assembly equipment, not a photograph of this model. Ask the manufacturer for current photographs and layout drawings of the configuration offered.

START WITH YOUR PRODUCTION TASK

Suits a line that switches between conventional and back-contact modules. Send HORAD your string layouts, choose which options you need, and measure transfer, placement and changeover time in a trial.

SOURCE-LINKED DATA

Published specifications

Values below are published by the manufacturer, each with the date its source was checked. Ask for the figures that apply to your configuration and material in the quotation.

The manufacturer has not published a complete specification table for this entry. Request the exact offered drawing and operating limits.

See sources and check dates ↓

01 · Manufacturer information

Strings in, arranged array out

Strings arrive from the stringer and the gantry places them automatically. HORAD says it can lay them horizontally or vertically and in AB or BC patterns. Flipping a string and cutting the solder strip are both optional. Drive is by linear motor and servo, with vision for positioning.

HORAD also says the machine moves between conventional and BC panels through a modular change it calls replacing panels, without saying which parts are swapped. Ask for the full tooling and template kit. The title says high-speed and the page mentions one-click switching, but neither comes with a cycle time or changeover time you could test against.

Source: HORAD BC high-speed gantry layup product page

02 · Manufacturer information

Format, utilities and the two machine envelopes

Format, utilities and the two machine envelopes
EntryCatalogue figureAsk HORAD
Module formatL 1630–2520 × W 1010–1450 mmWhich cell and string arrangements fit, and in which combinations.
Supply and power380 V / 22 kWLoad and supply details.
Plant air0.6–0.8 MPaConsumption and filtration level.
Machine size, L × H × W3600 × 2000 × 600 mm + 3600 × 2450 × 4255 mmTwo envelopes are listed; get the full layout and interface drawing.
Weight4.5 TFoundation and transport needs.

Source: HORAD BC high-speed gantry layup product page

03 · PVYard procurement analysis

Order the options by name

  • Layout and polarity

    Attach drawings of the horizontal, vertical, AB and BC patterns you run, with polarity. Confirm which patterns are supported and how the stringer hands strings over.

  • Flipping

    If strings must be turned over, add the flip option and ask for gripper and contact details for your string. Check cell condition after flipping in the trial.

  • Solder-strip cutting

    Supply the strip drawing and where cuts are allowed. Agree how offcuts are collected and how cut quality is checked, apart from placement. If busbar joining should happen in the same footprint, look at HORAD's BC layup and soldering integrated machine as well.

  • Changeover kit

    List the tooling, templates, recipes and operator steps for each module type. A one-click recipe switch can still involve swapping hardware by hand.

Source: HORAD BC high-speed gantry layup product page

04 · PVYard procurement analysis

Proving your layouts on the gantry

  1. Fix strings and tooling

    Record cell and string size and thickness, the orientations you need, the grippers and every ordered option against a controlled layout.

  2. Check position and damage

    Using agreed reference points and typical strings, measure where they land, look for handling damage and test recovery when input varies.

  3. Time a changeover

    Switch between conventional and BC set-ups with the real tooling and recipes. Log the time taken and check the first array afterwards.

  4. Connect to the line

    Test string supply from upstream, glass positioning, downstream ready signals and fault recovery. Write the agreed sustained output into the contract.

Source: HORAD BC high-speed gantry layup product page

05 · PVYard procurement analysis

Questions on the BC gantry

Do flipping and strip cutting come as standard?

HORAD lists both as options. Put the exact set you need in the quotation and the acceptance plan.

How fast is high-speed?

The page gives no cycle figure. Ask HORAD for one on your layout and time it in the trial.

Is the one-click change only software?

The page also mentions replacing parts. Ask which tooling is swapped and what the operator has to do.

Source: HORAD BC high-speed gantry layup product page

TURN THIS INTO A CLEAR REQUEST

Ask about this product

Include the product-specific questions above and replace every bracket with your actual requirement. Save your edited text to your sourcing brief, then review it before submitting an enquiry. Saving a brief does not send it to a manufacturer.

Sources

Manufacturer information and our buying guidance are labelled section by section above. Each source below shows the date it was checked.

HORAD BC high-speed gantry layup product page ↗

Source check: 2026-10-11 · Layout modes, optional flipping and strip cutting, and the two-part machine size.

Report a correction · How we prepare listings

Compare equipment for a related task